Company history

Our History

Our success is driven by a culture of continuous improvement and innovation. We embrace new technologies and industry best practices to enhance our operations and deliver superior results. With a focus on integrity, professionalism, and sustainability, Texas Powertech is committed to shaping the future of the contracting industry while contributing to the growth and success of our clients and communities.

2008
YEAR

THE BEGINING

  • Company Established – Texas PowerTech was founded with a vision to provide advanced power solutions.

  • KM Approved Product – Launched MAICO Cable Cleats, setting the foundation for future innovations.

2010
YEAR

2009 – Expanding Our Reach

  • Secured a major project with M/s. Debaj/ABB – Mesaieed, marking our early success.

2010 – Substation Projects Begin

  • Partnered with Larsen & Toubro (LnT) for the 66/11KV EDC (3,4,5) Substation Project, establishing our expertise in substation work.
2012
YEAR

2011 – Growth in High-Voltage Infrastructure

  • Delivered 66/11kV Al Merghab S/S in collaboration with Hyosung.
  • Executed 132/11KV Substations in Al Dhakirah, Umm Salal Central, and Al Karana with LnT.

2012 – Large-Scale Projects in Qatar

  • Partnered with Hyosung for 220/66/11kV Substations (Naeeja Super, Bani Hajir Super, New Doha B Super).
  • Provided cable management solutions for Qatar Museums.
2014
YEAR

2013 – Expansion into Logistics & Industrial Substations

  • Hyosung: Delivered 220/66/11kV Ain Khalid Super S/S & 66/11kV Al Wadi West S/S.
  • LnT: Worked on 132/11kV Logistic Village S/S & 220/66/11KV Doha Industrial Super S/S.

2014 – Powering Strategic Locations

  • LnT: Completed 220/66/11KV Duhail Super S/S and 132/66/11 KV Al Gharafa S/S.
2016
YEAR

2015 – Quality & Certification

  • Achieved ISO Certifications (9001:2015, 14001:2015, 45001:2018), reinforcing our commitment to quality and safety.
  • LnT: Completed 132/11kV Substation at Halul Island (Qatar Petroleum).
  • Delivered 220/66/11kV New Port Super S/S & 220/66/11kV Meherja Super S/S.

2016 – Strengthening Grid Networks

  • Partnered with Siemens for the 66/11kV Khalifat 2 S/S project.
2019
YEAR

2017 – Major Lusail City Projects

  • NCC: Completed 66/11kV Bufasilah S/S.
  • LnT / LREDC: Successfully delivered 7 Lusail substation projects, including Lusail West, Lusail North, Lusail Wadi, and Marina District Cooling Plant.

2019 – Industrial & Renewable Energy Initiatives

  • QIMC/KLJ: Delivered The Caustic Soda Factory.
  • BBC: Built 132/11kV Al Wukuair-4 S/S.
  • Siemens: Executed 66/11kV Meherija 1 S/S.
  • QATALUM / Hitachi Energy: Led maintenance of 200MVA / 60MVAr Shunt Reactors.
  • Siemens: Installed 132/11kV Izghawa North-2 S/S.
2021
YEAR

2020 – Powering Key Industries

  • MWANI / Siemens: Completed 22kV Package S/S (3 Nos.).
  • Qatar Steel / Siemens: Executed 6.6kV Bus Duct Installation Works.
  • Siemens: Delivered 132/11kV Bin Mahmoud-2 S/S & 132/11kV Mazrouha S/S.

2021 – Innovation & Energy Efficiency

  • Siemens Energy: Developed 66/11kV Wadi Al Sail S/S & 66/11kV Luaib S/S.
  • GE: Executed WAMS Project (LTC-1196/2017).
  • Hitachi Energy: Repaired 2 Nos. of 200MVA Transformers (LTC1430).